Welcome to The Gigacasting Newsletter

New here? Subscribe

Volkswagen Scraps Its Wolfsburg Gigacasting Centre

Volkswagen has ended its Gigacasting production project for cost reasons and will not build the large-casting centre planned at its Wolfsburg home plant. Ground-breaking for the new casting hall was due next week.

The decision was taken at the latest meeting of the Group Board of Management and was first made public on 11 November 2026 by the works council in a special edition of its staff paper, Mitbestimmen. A company spokesperson then confirmed it: "Against the background of the company's tense economic situation, all investments are currently under review.

This goes hand in hand with the decision not to build the planned large-casting centre at the Wolfsburg site. Volkswagen stresses that development of its next electric platform, the Scalable Systems Platform (SSP), continues as planned, and that it still aims to make production of the next vehicle generation "simpler, more efficient and more competitive" in all its plants.

Credit: Martin Lagler

Gamechanger was the package of new production methods, large castings of body parts among them, that a cross-departmental team had been working on for years and that was meant to debut in Wolfsburg before spreading to the rest of the group. According to the works council, the SSP models for Wolfsburg, an electric Golf and an electric model in the T-Roc segment, will still come, but "apparently mainly with the existing, conventional methods" rather than the new processes. Handelsblatt reports, citing people familiar with the matter, that the cut is also linked to Audi's planned US plant in Georgia.

Works council chief Daniela Cavallo calls the move "a flagrant breach of our agreement from December 2024" and says the board is abandoning its own claim to technology leadership in manufacturing: "Only short-term profit thinking is in the foreground now." As leverage, she says the combustion Golf will not leave Wolfsburg for Mexico until the workforce gets full transparency on staffing, volumes and timing.

That December 2024 agreement had settled a dispute over plant utilisation: Wolfsburg would get the new production methods, including large castings, for the electric Golf and T-Roc, while the combustion Golf would move to Mexico. By then the group had already built up casting know-how at its Kassel foundry, Europe's largest die-casting operation, which opened a Large Castings Competence Centre in February 2024. Its management argued at the time that presses above 4,000 tonnes only make sense right next to vehicle assembly.

Credit: Volkswagen

At IAA Mobility in September 2025, Volkswagen showed its first large-casting application, a battery-tray frame for the ID. Polo, Cupra Raval, Škoda Epiq and ID. Cross. Cast on a 4,400-tonne machine (4,800 ton in series), it replaces 123 parts, cuts weight by 10% and costs by 15%. Front and rear underbody castings were still undecided, although new facilities with 8,400-tonne machines were floated. This summer that question seemed settled when Bühler received an order for around 16 machines of 9,200 tonnes for front and rear underbody castings on the next-generation platform.

Credit: Volkswagen

The squeeze then reached the products. At the end of October Volkswagen paused development of the next Golf, the ID. Golf, with brand chief Thomas Schäfer saying "we simply cannot afford this work right now". Two weeks later the casting hall followed.

None of the reports says what happens to the Bühler machines. The Wolfsburg hall was where the group's new large-casting methods were supposed to start. With that hall cancelled and the first SSP cars, according to the works council, built mainly with conventional methods, no source says where large castings for the next platform will now be made. Machine-by-machine status in The Gigacasting Database.

Multiple sources of The Gigacasting Newsletter familiar with the matter confirmed the Automobilwoche report.

Utah Picks Mariana Minerals To Redevelop The Former US Magnesium Site At Rowley

On 5 November, the state of Utah selected Texas-based Mariana Minerals to plan the “responsible redevelopment” of the former US Magnesium facility at Rowley, in Tooele County on the Great Salt Lake. Utah bought the 4,500-acre site earlier this year for $30 million. Mariana is to map a phased restart of lithium and magnesium extraction there, using newer, non-evaporative, lower-water technology.

Governor Spencer Cox called the choice a “significant win,” arguing that Utah is replacing a legacy polluter with an operator whose technology would protect the lake’s water and whose royalties could fund cleanup of the Superfund site instead of passing that cost to taxpayers. Mariana, which already runs Copper One in San Juan County, would replace the plant’s large industrial solar-evaporation diversions with a new low-water processing system.

Co-founder and CEO Turner Caldwell described a proposed, phased restart of lithium and magnesium production that prioritizes water conservation, cuts historically difficult air and wastewater emissions, and brings remediation funding forward sooner. The company has agreed to operate under a modernized lease from the Utah Division of Forestry, Fire and State Lands. Utah and Mariana are still working to finalize the specific redevelopment terms, including the regulatory frameworks and milestones for the site’s updates and cleanup.

That $30 million is what the state paid for the site. Separately, Shanghai Metals Market reported Mariana as the bidder for remaining Rowley assets at $16.5 million in cash plus royalties.

Source: Spenser Heaps, Deseret News (via KSL)

Source: Spenser Heaps, Deseret News (via KSL)

US Magnesium had run the Rowley plant for decades before it ceased mineral operations five years ago after equipment failures, and filed for bankruptcy last year. The company and the state had clashed over pollution and water use; Utah claimed that 50,000 to 80,000 acre-feet of water was still leaving the Great Salt Lake each year even when minerals were not being extracted.

When the assets went to auction in January, Utah outbid LiMag Holdings, a company with ties to US Magnesium’s primary owner, and took the property together with nearly 145,000 acre-feet of water rights. The legislature funded the purchase from a rainy-day account. In February, environmental quality commissioner Tim Davis warned that the state had also taken on a Superfund site that would likely take years, and significant cost, to clean up.

Sources: KSL, SMM

Atlas Materials Gets Anc Investment From SMGM For A Planned 23,000 Ton Magnesium Plant

Atlas Materials, the Delaware company formally named Negative Emissions Materials Inc., said on 11 November that Société Minière Georges Montagnat (SMGM), a miner in New Caledonia, has completed a strategic investment in the company. Together with funds Atlas already holds and a planned US$9 million capital raise, the investment will support the engineering work, the definitive feasibility study, the permitting and the development of Atlas’s first commercial-scale plant, which is expected to produce about 23,000 tonnes of primary magnesium metal a year.

Atlas says it is in the final phase of assessing a short-list of sites in North America and Australia. The process would take saprolite ore supplied by SMGM and yield high-purity magnesium metal, a nickel-cobalt mixed hydroxide precipitate and other by-products. Atlas already has a long-term supply agreement with SMGM for that ore, and in June 2025 the Government of New Caledonia approved SMGM’s export of up to 200,000 wet tonnes a year to support industrial trials. Atlas says the planned 23,000 tonnes a year would be equivalent to around 30% of current US consumption.

In June this year Atlas also said it had produced high-purity magnesium metal from oxide made with its process, working with Andritz on the oxide and converting it to metal by aluminothermic reduction at a facility operated by Big Blue Technologies. That work was done with partners, not at a commercial Atlas plant.

Photo: Atlas Materials

Photo: Atlas Materials. Paul Newling, MD of NewPro Engineering, Ken Baxter, SVP of Engineering at Atlas Materials, David Dreisinger, CEO at Atlas Materials, Pierre Charlent, Adviser on Geology and Nickel Ore Procurement at Atlas Materials

The planned plant would place Atlas among a small group of Western projects aiming to rebuild primary magnesium supply outside China, each on a different timetable and feedstock. In Australia’s Latrobe Valley, Latrobe Magnesium Limited is commissioning a demonstration plant that would recover magnesium from industrial ash left by brown-coal power stations, with first metal still targeted by the end of 2026. Separately, it is pursuing a commercial plant in Colleton County, South Carolina, whose first train is sized at about 50,000 tonnes a year, with room on the same site for a second train that would take the complex to about 100,000 tonnes.

That American plant would run on a different New Caledonian feedstock: ferronickel slag from Société Le Nickel (SLN), the nickel company inside the French group Eramet, under a 20-year memorandum of understanding. South Carolina remains a preferred location, with a feasibility study and a final investment decision still ahead and first production targeted around April 2030.

Haitian Trials a 7.2 kg Magnesium Tailgate Inner on a 7,000 T Machine

Haitian Metal, together with Seres, Waffer Technology and Baowu Magnesium, has trial produced a large semi solid magnesium tailgate inner panel on its 7,000 ton magnesium double-injection thixomolding machine. Haitian presents the panel as the first large structural part made by magnesium double injection molding.

The company says the machine's twin injection units shorten the path the metal has to travel, and that the injection control system produces a complete fill and a dense structure, with better dimensional accuracy and strength than conventional die casting. Haitian gives the trial part an average wall thickness of 2 mm and a weight of 7.2 kg, nearly 50% lighter than a conventional steel tailgate inner.

Photo: Haitian Zhisheng Metal

Photo: Haitian Zhisheng Metal

Haitian first presented the 7,000 ton machine at China Die Casting in Shanghai in July 2025, with production readiness planned for later that year, and a twin-injection system intended to raise the volume of magnesium that can be shot into the die. In October it published the first pictures of the press, and an illustration already showed a tailgate on one side and a door on the other, to be filled in synchronous or asynchronous injection.

In November 2025, Waffer opened a lightweight-materials research centre and a magnesium application centre together with Haitian and the Magnesium Alloy Engineering Research Center of Chongqing University, and installed five Haitian thixomolding islands, the 7,000 ton machine among them. The press has a clamping force of 70,000 kN, two 180 mm screws and a shot weight of more than 38 kg.

Photo: Haitian Zhisheng Metal

Source: Haitian Zhisheng Metal, via Zhuzao Toutiao (11 November 2026); Die Casting Weekly (13 November 2026).

Quick News

Lexus Confirms Its First Shanghai Model Is An Electric SUV

Lexus will put its first China-built vehicle on sale in 2027, a battery-electric SUV from its new plant in Jinshan, Shanghai. Initial output is planned at around 1,000 units a month, and Electrek says production is due to rise to “tens of thousands” in 2028.

CarNewsChina, citing Autohome, says the plant will use front and rear aluminium structural castings, bringing several components into larger pieces, and a conveyor-free layout in which vehicles move between workstations on their own.

The wholly owned Jinshan plant is due to start production in 2027 and will be the first place where Toyota uses giant presses in series production. Over the summer two 9,000 ton Gigacasting cells from Haitian were installed into the plant.

Photo: Autohome, via CarNewsChina

Photo: Autohome, via CarNewsChina

Source: Electrek — 2 November 2026; CarNewsChina (via Autohome) — 31 October 2026.

Verde Magnesium Opens Equipment Procurement For Its Romanian Project

Verde Magnesium has opened a new equipment procurement for its planned primary-magnesium operation in Romania, covering material preparation, aluminothermic reduction, research and development, and automation. The package follows earlier tenders for refining and casting equipment.

The company’s plans envisage production beginning at about 360 tonnes a year in 2028, rising to around 30,000 tonnes a year in 2031. The project could potentially reach 90,000 tonnes a year by 2036.

The project already has Strategic Project status under the European Union’s Critical Raw Materials Act, for both extraction and processing. Verde has planned to start with a first unit in Beiuș, then a larger smelter; in September the company was still waiting on European Union funding for that first plant.

Source: Europe Mining News — 5 November 2026.

China’s Primary Magnesium Output Reaches 961,200 Tonnes Through October

China’s primary magnesium output was 91,000 tonnes in October 2026, up 5.69% month-on-month and down 0.2% year-on-year, according to incomplete statistics from the Magnesium Branch of the China Nonferrous Metals Industry Association. Cumulative January–October output was 961,200 tonnes, up 17.51% year-on-year.

By region for January–October: Shaanxi 668,200 tonnes (+28.65% year-on-year); Shanxi 132,500 tonnes (−16.98%); Inner Mongolia 26,500 tonnes (−16.93%); Xinjiang 48,400 tonnes (+5.68%); other regions 85,600 tonnes.

Through August the same series had put January–August output at about 784,100 tonnes, up 23.03% year-on-year. Growth is still concentrating in Shaanxi, while Shanxi and Inner Mongolia continue to contract.

Source: Die Casting Weekly (yzweekly) — 13 November 2026 (China Nonferrous Metals Industry Association Magnesium Branch, incomplete statistics).